How do we turn a subdivision permit into an executable works programme?
Create a condition register listing each requirement, responsible consultant or trade, evidence needed and the milestone it controls. Separate civil works, authority connections, landscape work and legal documentation from the house build. Check the actual permit rather than copying another council’s checklist. Review the register at design changes and before ordering affected work, so a service corridor, driveway or planting requirement is coordinated while changes are still manageable.